City of Decorah is beginning planning for repaving East Main Street

Posted: Sun, Jan 3, 2021 9:23 AM

The City of Decorah has hired Erdman Engineering to draw up plans for the reconstruction of East Main Street.

The firm will be paid a total of $98,500 for its work to provide professional services to the city.  That work will include creating plans for the reconstruction of East Main Street from mid-block between State State and Day Street east through the Williams Street intersection.  Additional work will be done if funding allows.

The project will also include the reconstruction of water main, sanitary sewer and storm sewer pipes under the street.  The scope of the sanitary sewer pipe replacements is still to be determined.